TOWN OF LANTANA PROJECT STATUS (2/18/21) | ||||
---|---|---|---|---|
Project | Description | Start | Est Completion | Status |
Lantana Nature Preserve | Replace Walking Trail and Repair Retaining Wall | 12/4/2020 | Phase I 99% Complete Opening to the Public 2/3/21. Permit Pending for Phase II | |
Town Wide Street Paving | Mill and Pave Streets Town Wide | 12/14/20 | 2/10/2021 | 99% Complete. Wrapping up Pavement Marking and Traffic Loop Repairs |
Police Department Emergency Generator | Install Electrical Connection, Pad and Enclosure | TBD | Bids Being Evaluated | |
Water Treatment Plant Fuel Tank Replacement | Replace Fuel Tanks for the Emergency Power Generator | Awarded 1/11/21 | Project Phasing Being Planned | |
Water Treatment Plant High Pressure Service Pumps | Replace High Pressure Service Pumps and Construct Bldg for Electrical System | TBD | Baxter & Woodman Preparing Bid Documents | |
W. Pine St. Water Main Replacement | Replace Leaking Water Main at FEC Railroad Crossing | TBD | Bids Being Evaluated. Going to Town Council for Approval 2/8/21 | |
Marine Safety Renovation | Renovate Marine Safety Bldg to Improve Air Quality and Repair Moisture Damage | Awarded 3/20/20 | Original Contractor Terminated for Failure to Perform. Going to Town Council for Approval of Next Lowest Bidder's Proposal 2/8/21 | |
Bicentennial Park Bathroom | Replace and Upgrade Restroom | Awarded 12/7/2020 | 5/20/2021 | Under Construction |
Bicentennial Park Playgound | Install New Playground for 2-12yr Old Children |
Awarded 2/8/2021 |
Estimated Complete Installation 6/4/2021 | |
Bicentennial Park Sculpture | Fabricate and Install Sculpture to Commemorate Town's Centennial | Awarded 10/26/20 | Contract Awarded. Fabrication Underway | |
Lantana Beach ADA Ramp | Construct ADA Compliant Beach Access Ramp | TBD | Pre Design Planning | |
Sea Pines Pump Station | Install Stormwater Water Level Control Pump System | TBD | Pre Design Planning | |
Sea Pines Swale Restoration | Community Wide Swale Restoration | TBD | Pre Design Planning | |
Sea Pines Basin Excavation | Excavate Stormwater Basin to Increase Capacity | TBD | Pre Design Planning |